Civcon has completed the Knostrop Surfacing Scheme for Yorkshire Water, its latest scheme for the water company after work at Eggborough treatment works.
About Knostrop
Knostrop is Yorkshire Water's largest wastewater treatment works, serving a population equivalent of around 990,000 people in and around Leeds. A site that size can't afford downtime, planned or not, which shaped how this scheme was programmed.
Appointed through the Yorkshire Water minor works contract, Civcon delivered a hazard resolution package across the site, commissioned specifically to improve safety for the people working there day to day.
The scope included verge hardening to create safe turning areas for HGVs and LGVs, replacement of damaged assets across the site, repairs to guarding and safety controls along gantries and raised walkways, and resurfacing of the three main access routes.
The wearing course specification was changed to a harder wearing material to extend service life under heavy plant traffic. The work was programmed across three shifts so all three access routes were completed without disrupting daily operations on a live treatment works, which is the part that takes the planning.
None of this could be done as a straightforward resurfacing job. A treatment works serving a population that size runs around the clock, so the three-shift programme had to work around what was already live on site, not the other way round. Recording checks like this, wearing course specification, shift sign offs and access route handovers, is the kind of quality control Civcon's ISO 9001 accreditation requires.
Lewis at Yorkshire Water on the result: "Civcon did a great job on the tarmacking works. The team were professional, efficient and delivered a high quality end product. It was a quality finish and we're pleased with the outcome."